Compaction grouting, also known as low mobility grouting, involves the injection of a low-slump mortar grout to densify loose, granular soils and stabilize subsurface voids or sinkholes.
Process
Low mobility grouting densifies loose granular soils (compaction grouting), reinforces fine-grained soils, and stabilizes subsurface voids or sinkholes by the staged injection of low-slump, low mobility aggregate grout. An injection pipe is typically inserted to the maximum treatment depth when performing soil improvement. The grout is injected as the pipe is slowly removed in lifts, creating a column of overlapping grout bulbs. The expansion of the low mobility grout bulbs displaces surrounding soils. Compaction grouting increases the density, friction angle, and stiffness of surrounding granular soils. The effectiveness of the improvement can be increased by sequencing the low mobility (compaction) grouting work from primary to secondary to tertiary locations. In all soils, the high modulus grout column reinforces the treatment zone.
Compaction grouting was developed in the 1950s as a remedial measure for the correction of building settlements. Over the past 25 years, low mobility grouting technology has evolved to treat a wide range of subsurface conditions for new and corrective construction. These include rubble fills, poorly placed fills, loosened or collapsible soils, karst conditions, and liquefiable soils.
Low mobility grouting often offers an economic advantage over conventional approaches such as removal and replacement or piling and can be accomplished where access is difficult, and space is limited. Low mobility grouting for treatment beneath existing structures is often selected because the low mobility grout columns do not require structural connection to the foundations.
Common uses
- Suitable for rubble fills, poorly placed fills, loosened or collapsible soils, karst conditions, and liquefiable soils
- Treatment beneath existing structures because columns do not require structural connection to the foundations
- Reduce liquefaction potential
- Decrease or correct settlement
- Increase bearing capacity
- Stabilize sinkholes or reduce sinkhole potential
Advantages
- Economic alternative to removal and replacement or piling
- Can be performed in very tight access and low headroom conditions
- Able to reach depths unattainable by other methods
- Non-destructive and adaptable to existing foundations
- Effective in a variety of soil conditions
Quality assurance
Keller's quality control includes procedural inspection and documentation of the work activity, testing to ensure proper mix design and injection rates, and verification of ground improvement where applicable. Ground improvement can be assessed by Standard Penetration Testing, Cone Penetrometer Testing, or other similar methods. Data recording of important grouting parameters has been utilized on sensitive projects.
Related projects
Infrastructure
Highway 401 Emergency Work
Keller provides emergency grouting to stabilize the roadway following settlement from nearby tunneling.
Infrastructure
Dey Street Connector
The Fulton Street Transit Center was constructed under the New York MTA’s Capital Construction Program to accommodate five subway stations handling nine lines. Keller completed various techniques, including dewatering and remedial grouting.
Dams and levees
Cannonsville Dam Emergency Remediation
Keller’s rapid response to developing and implementing an emergency groundwater control plan was key to quickly resolving a subsurface issue threatening dam stability.
Commercial
Montgomery Multiplex Floor Slab Repairs
The City of Montgomery manages the Multiplex at the Cramton Bowl, a 70,000 SF indoor facility that hosts numerous sporting events and training clinics throughout the year.
Infrastructure
Nesbitt Dam
Nesbitt Dam, constructed in 1901, is a composite earth embankment and stone masonry structure, 101 ft high and 538 ft in length. The dam is partially founded on a rock outcrop that transitions to glacial till. A masonry core wall extends the full height of the dam.